Project Timeline
The City Council will review the conceptual plans and request to authorize submittal of a River Parkways Grant application on September 24, 2007. The School Board’s review of the conceptual plans and request to authorize a support letter of the City’s River Parkways Grant application will occur on September 25, 2007. Once the City Council and School Board have approved the conceptual plans and the grant application has been submitted on October 19th, work will begin on the construction drawings. The grant awards are anticipated to occur in June 2008. We anticipate completing the construction documents prior to the grant awards so that we may start the project before the start of the Los Angeles County Official 2008-2009 Rainy Season. The following table includes the currently anticipated timeline for the project:
| Task |
Time Frame |
| Project study, community workshops and conceptual design |
July – September 2007 |
| City Council Approval of Conceptual Design & Authorize River Parkways Grant proposal submission |
September 24, 2007 |
| School Board Approval of Conceptual Design & Authorize support letter of City’s River Parkways Grant proposal submission |
September 25, 2007 |
| River Parkways Grant application submission and begin preparing final plans/specifications |
October 19, 2007 |
| Council approval of plans & specifications and authorize release of request for bids. |
May 2008 |
| School Board approval of plans and authorization to work on District property |
May 2008 |
| Award construction contract |
August 2008 |
| Begin construction |
August or September, 2008 |
| Complete construction |
January or February, 2009 |