| Initiative |
Priority |
Comment |
Status |
| Continue to Replace CRT monitors with Energy Star Flat Panels |
1 |
Flat panel monitors are about 30% more efficient than CRT. In addition to this direct savings, since CRTs generate more heat there will be savings in air conditioning. |
The city began replacement of CRT monitors in 2005. There are approximately 80 CRT monitors yet to be replaced. Al will be replaced by fall 2008. |
| EPEAT certification for all desk top PCs purchased |
1 |
EPA supported EPEAT certifies PCs in categorizes bronze, silver and gold. www.epeat.net |
Early in 2007 the department began a policy of purchasing PCs that were certified at a minimum “silver” certification. This policy will remain in effect. |
| Meter Power Use in Data Center |
1 |
In order to effectively control power use it must be measured |
Currently, (as of 12/07) working with Public Works to install metering of power to the Data Center. |
| Implement Server consolidation(virtualization) |
1 |
Server consolidation is one of the top strategies suggested by the EPA report. |
Staff report to City Council 12/07. Implementation will begin in February 2008. |
| Research raising temperature in Data Center |
1 |
We may be over aggressive in cooling the Data Center. Raising he temperature will reduce indirect cost and power use for AC |
Implement optimal temperature in January 2008, after metering is implemented. |
| Research network power off Desktop PCs |
2 |
To ensure that all PCs are powered off during off work hours, IT will affect the shut down via our network. |
Research to be conducted by Technical services staff. Implement spring 2008. |
| Implement Storage virtualization |
1A |
Storage virtualization has the potential of saving energy on a scale similar to server virtualization. |
Implementation consideration will begin soon after we begin server virtualization as part of our overall virtualized environment. Staff report to Council in July 2008. |
| Research Desktop virtualization |
3 |
Virtual Desktop Infrastructure (VDI) may produce energy savings if this, or similar technologies are implemented. |
Availability of staff resources will put off this project until fall 2008, at earliest. |
| Energy use profile of UPS and air conditioning |
1 |
Energy efficiency can range from 80-95%. We need to ensure that we are using high efficiency UPS and AC. |
Complete by January 2008. |
| Include environmental language in contracts and purchasing for hardware |
1 |
Environmental related Contract and Purchasing language should reflect “in practice” policies. |
Review with Purchasing and City Attorney. Complete by February 2008. |
| Produce a semiannual report on status and progress for the City Manger, City Council, and public. |
1 |
To ensure continual review of and priority of environmental impact of IT. |
Update web site as action items change. Written review/report in June and January each calendar year. |
| Review Data Center Structure |
3 |
There may “construction related” issues that could be addressed that could increase the cooling efficiency of the room. |
Identify any cost effective action that could be implemented. Complete by June 2008. |